How do I import Work Order items into a Change Order Request or Change Order?

Skip to main content
How can we help you today?

Our Knowledge Base contains the answers to more than 500 previously asked questions.

Create a Ticket Schedule a Training

At this time, it is not possible to import Work Order items directly into a Change Order Request or Change Order in Contractor Foreman.

Here’s why:
Once a Work Order is approved, and if it is marked as a Cost Work Order, its value is automatically added to the Schedule of Values (SOV). This means the system already accounts for the scope, cost, and contract value of that Work Order. In other words, you don’t need to duplicate the same scope again in a Change Order, the Work Order has already updated the project’s financials.

Why this makes sense

  • It avoids double-counting project revenue or costs.

  • Keeps the financial workflow clean and accurate.

  • Ensures that each tool, Work Orders vs. Change Orders, is used for its intended purpose.

Best practice

If the client requests additional work not covered by the Work Order, that’s when you should create a Change Order. Use Change Orders for true changes to the original contract scope, while Work Orders should be used to add entirely new scopes of work or internal assignments.

Was this article helpful?
3 out of 5 stars

2 ratings

5 Stars 50%
4 Stars 0%
3 Stars 0%
2 Stars 0%
1 Stars 50%
5
How can we improve this article?
Please submit the reason for your vote so that we can improve the article.