How Purchase Orders Transfer Between Contractor Foreman and QuickBooks

Skip to main content
How can we help you today?

Our Knowledge Base contains the answers to more than 500 previously asked questions.

Create a Ticket Schedule a Training

Introduction:
Accurate purchase order (PO) synchronization between Contractor Foreman and QuickBooks is essential for maintaining clear financial records and proper job costing. This article explains how Purchase Orders are transferred in both directions—from Contractor Foreman to QuickBooks, and from QuickBooks to Contractor Foreman—and outlines best practices for using them effectively.


How Purchase Orders Transfer from Contractor Foreman to QuickBooks

When a Purchase Order is created in Contractor Foreman, it transfers to QuickBooks with all critical information intact, provided the integration is active and properly configured.

Information Transferred Includes:

  • Supplier details
    • Supplier name
    • Supplier address
  • Shipping details (if a Project is selected)
    • Ship To
    • Shipping Address (Project address)
  • PO details
    • Purchase Order Date
    • Ship Via
    • Purchase Order Description
  • Line item details
    • Product or Service
    • Description
    • Quantity
    • Rate

All of this data maps directly to the corresponding fields in QuickBooks, ensuring seamless accounting and purchasing documentation.


How Purchase Orders Transfer from QuickBooks to Contractor Foreman

Purchase Orders created in QuickBooks can sync to Contractor Foreman, but there are limitations that can affect accuracy—especially in job costing.

Important Note:
If you enter Purchase Orders directly in QuickBooks, you must use the Item Details section, not the Category Details.

Why?

  • Item Details allow the use of Cost Codes, which are essential for job costing in Contractor Foreman.
  • Category Details do not support cost codes and therefore do not integrate correctly for project-based reporting in Contractor Foreman.


Recommended Workflow

To ensure clean data and accurate reporting:

  1. Create Purchase Orders in Contractor Foreman first.
    This ensures that all details, including cost codes, project associations, and supplier data, are properly structured and sent to QuickBooks.
  2. Let Contractor Foreman push the PO to QuickBooks via the integration.
    This reduces duplication, avoids incorrect cost tracking, and ensures smoother audits and reporting.

Best Practices

  • Always create POs in Contractor Foreman when job costing is important.
  • Use Item Details only if creating POs in QuickBooks.
  • Make sure Suppliers are properly synced between systems to avoid duplication.
  • Allow up to 5 minutes for sync completion between systems.
Was this article helpful?
0 out of 5 stars
5 Stars 0%
4 Stars 0%
3 Stars 0%
2 Stars 0%
1 Stars 0%
5
How can we improve this article?
Please submit the reason for your vote so that we can improve the article.