Recommended Workflow to Run a Cost Plus Project

Skip to main content
How can we help you today?

Our Knowledge Base contains the answers to more than 500 previously asked questions.

Create a Ticket Schedule a Training

A complete workflow guide — from good faith estimate to final closeout

Skill level: Intermediate–Advanced
Modules covered: Estimates, Invoicing, Bills, Timecards, Expenses, Job Cost Reports, Change Orders

 

A Cost Plus contract is an agreement in which a contractor is reimbursed for all direct project costs — labor, materials, subcontractors, equipment — and receives a predetermined fee on top of those costs as their profit. Unlike a fixed-cost contract where your margin is baked into the estimate and you absorb any overruns, in a Cost Plus arrangement the client pays what the project actually costs. Your profit is protected regardless of what happens to material prices or scope.

For projects with significant ambiguity — renovation work where walls haven’t been opened yet, commercial builds with incomplete drawings, or any job where unforeseen conditions are likely — Cost Plus is often the smarter structure. It protects your margin and creates transparency with the client from day one.

There is no “Cost Plus” toggle in Contractor Foreman. It’s not a setting — it’s a workflow. This guide walks you through that workflow from start to finish.

Before you start, clarify two things with your client: (1) Is your fee calculated as a markup on cost or a margin on total sales? These produce different numbers. (2) Is a deposit required at signing?

Step 1 — Build the good faith estimate

In a fixed-cost project, the estimate is a commitment. In Cost Plus, it’s a good faith projection — your best estimate of what the project will cost, with the understanding that actual costs will be billed as they are incurred. The client may spend more or less than this number. That’s the nature of the contract.

Structure your estimate by trade, phase, or scope of work — whatever mirrors the construction sequence most closely. This matters because your estimate becomes your Schedule of Values once the project is created, and your invoices will follow the same structure. If your estimate is organized clearly, your billing will be too.

Turn off markup on all line items. This is the single most common mistake on Cost Plus estimates. Every cost you incur gets passed to the client at face value — there is no per-line markup. If you’re importing items from your cost item database, check each one: markups can carry over silently and inflate the estimate without you noticing.

Adding the contractor fee — the “Plus”

Your profit does not come from line item markup. It comes from a single dedicated fee line item, added as its own section at the bottom of the estimate. Here is how to set it up correctly:

Item type: Other
QTY: 1 | Unit cost: $0.01
Switch markup to $ (dollar) mode and enter your fee amount directly
Assign it to its own cost code — for example, “Construction Mgt Fee”

Setting the unit cost to one cent is intentional. It keeps your actual costs out of this line item so the Job Cost report doesn’t conflate your fee with your project expenses. The markup field holds the real number.

Before moving on, verify the profit amount shown at the bottom of the estimate. Markup and margin are not the same calculation: a 20% markup on $100 in costs produces a $20 fee and a $120 total. A 20% margin on a $120 total produces a $24 fee. Confirm with your client which method applies and check that the estimate reflects it.

Adding the deposit line item

If your contract requires a deposit at signing, add a $0.00 line item to a separate section — label it “Deposit” or “Advance Payment” — and assign it to its own cost code (for example, “Customer Deposits”). This cost code should be tied to a liability account in QuickBooks, since a deposit collected before work begins is a liability on your books until it is earned. You will use this line item later when creating the deposit invoice and again when applying the credit to a future invoice.

Step 2 — Approve the estimate and create the project

Submit the estimate to the client for approval. Once approved, create the project in Contractor Foreman. The system automatically generates a Schedule of Values from your estimate structure — every section and line item carries over. This SOV is the reference point for all future invoicing on the project.

Step 3 — Process the deposit

Once the client approves and sends their deposit, create an invoice for the deposit amount using the Customer Deposits cost code. Post the payment, mark the invoice paid, and email a copy back to the client as their receipt. The deposit now sits on your books as a liability and will be credited against future invoices as the work is performed.

Step 4 — Track costs as work proceeds

This is where Cost Plus lives or dies. Every dollar you spend on the project needs to be entered in Contractor Foreman and assigned to the correct cost code. Bills from vendors, bills from subcontractors, timecards, and expenses — all of them. If a transaction has no cost code, it won’t appear in your Job Cost report, which means you can’t bill it accurately and you can’t show the client where their money went.

Always assign a cost code when entering bills, timecards, and expenses. A transaction without a cost code is invisible in job cost reporting. In Cost Plus, that’s not just a data quality problem — it’s a billing problem. You cannot invoice a cost you cannot see.

Step 5 — Invoice periodically

To create a progress invoice, start by running the Job Cost Actual Report for the billing period. This report shows you exactly what was spent per cost code — those are the numbers you will bill the client. Once you have those figures, create your invoice from the Schedule of Values, updating each line item to reflect the actual costs incurred for the period rather than the estimated amounts.

Once the costs are entered, manually calculate your contractor fee for this period (total costs × your fee percentage) and add it as a separate line item on the invoice. Do not forget this step — it’s easy to miss when you’re focused on getting the cost details right.

If you collected a deposit or advance payment, apply it on this invoice or a future one by adding a line item with a quantity of -1 referencing the deposit amount. This reduces the invoice total and shows the client clearly how the advance is being drawn down.

Attach the Job Cost Transactions report as backup with every invoice. Transparency is the foundation of a Cost Plus relationship. It shows the client every bill, expense, and timecard that drove the invoice — organized by cost code and date. It’s one of the most effective tools for building trust with clients who are newer to this contract structure.

 

Step 6 — Monitor the Job Cost Actual Report regularly

Run the Job Cost Actual Report at least as often as you invoice. This report shows you, for each cost code: what you estimated (contract value), what you’ve invoiced to date, and what you’ve actually spent. The gap between those numbers tells you what action to take.

If actual costs have exceeded the estimated amount on a cost code, that overage belongs to the client — create a change order to bill them for the additional cost. If actual costs came in under the estimate, the savings belong to the client too — create a negative change order to credit them. In a Cost Plus contract, the variance in either direction is the client’s money, not yours. The only profit you keep is your service fee.

Change orders on a Cost Plus project follow the same structure as the estimate: no line item markup, and a separate contractor fee line item for the fee you earn on the additional or reduced scope.

Step 7 — Final invoice and project closeout

Create the final invoice from the SOV using the actual remaining costs, add the contractor fee for the last period, and apply any remaining deposit credit as a negative line item. At this point all costs should be accounted for and all advance payments should be fully drawn down.

Before closing the project, run the Job Cost Transactions report as a final audit. Every bill, expense, and timecard on the project should appear on an invoice. If any costs were entered but never billed, this is your last opportunity to catch them.

If the Job Cost Actual Report still shows a variance between the contract value and the amount invoiced — which it often will, because estimates are rarely exact — create an internal reconciliation change order to bring those numbers into alignment. This is an optional but strongly recommended step: it keeps your project data clean and makes the cost history accurate when you look back at this project as a reference for future bids.

Finally, print the Project Statement from Contractor Foreman and email it to the client. This document shows the original contract amount, all change orders, all invoices issued, all payments received, and the remaining balance. It’s a clean, professional closeout summary that gives the client a complete picture of the project in a single page.

Summary — the Cost Plus workflow at a glance

Build a good faith estimate with cost codes, no line item markup, and a separate contractor fee line item at $0.01 cost
Add a deposit line item under its own cost code if a deposit is required
Approve the estimate, create the project, and collect the deposit via invoice
Enter all bills, timecards, and expenses with cost codes assigned — every transaction, every time
Invoice periodically from the SOV using the Job Cost Actual Report to determine amounts, adding the contractor fee manually and applying deposit credits as negative line items
Monitor the Job Cost Actual Report to catch overruns and savings, and issue change orders accordingly
Close out with a final invoice from the SOV, a reconciliation change order, and a Project Statement to the client.

What if your customer wants a complete breakdown of the job costs—every time card, bill, and expense?

You can provide that information using the Job Cost Actual Report (Detail). The report’s second tab shows the individual entries, which you can filter by date, cost code, and other criteria. It gives you a straightforward way to share a detailed record of what has been spent on the job in one document.

The accuracy of the report depends on how consistently and correctly bills, expenses, and time cards are entered into the system. Make sure each entry is assigned to the appropriate project and cost code.

To access the report, go to Main Menu → Documents → Reports → Job Cost, then select Job Cost Actual Report (Detail).

For more information, feel free to download this presentation or schedule a 1-on-1 training session.

Was this article helpful?
0 out of 5 stars
5 Stars 0%
4 Stars 0%
3 Stars 0%
2 Stars 0%
1 Stars 0%
5
How can we improve this article?
Please submit the reason for your vote so that we can improve the article.